Project Description
SOMAC’s work consisted of the procurement and construction of an extension to an existing utility bridge, including culverts.
Avada domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home4/somaccon/public_html/wp-includes/functions.php on line 6121fusion-builder domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home4/somaccon/public_html/wp-includes/functions.php on line 6121| Client | Royal Commission of Jubail and Yanbu (RCJY) |
| Value | SAR 3-5mn |
| Start-end-dates | 2003 - 2004 |
| Consultant | Saudi Arabian Bechtel Company |
SOMAC’s work consisted of the procurement and construction of an extension to an existing utility bridge, including culverts.